Hi,
I got a weird behavior when running Master Sched. Here is my case:
I run Job Scheduling. BOM w/ 5 components (all one for one).
Basic Data: Nothing is reserved before the calc is run (period Coverage
Code) + 0 on hand for all Parent and component. I placed a SO for 1 piece due
in 20 days from now. The result is giving me exactly what i wanted. But i
changed the SO date in 10 days from now.
Result: The planned Purchase orders for the 5 components have a Req. Qty of
2 instead of 1 just by changing SO date. There is no other requirement other
than the SO. The period time fence is 30 days and coverage 365. My question
is: How can MSched can give me a req. qty greater than my requirement?
|