Hi,
Basic Setup: 1 parent w/ 5 component (Item Type), coverage time fence 365
and period 30...this coverage is for the parent only i did not put coverage
data on component. I got 0 on hand for the 6 items.
Case 1. Positive Days @ 7
Today's date: August 14
Sale Order Date: Agust 31
The result: 1 planned production Order and 5 planned Purchase Order
Assumption: 31-14 = 17 days - 7 (pos. d.) = 10
Case 2. Positive Days @ 8
Today's date: August 14
Sale Order Date: Agust 31
The result: 1 planned production Order
Assumption: 31-14 = 17 days - 8 (pos. d.) = 9
I don't know if it's related to positive date but instead, i changed the SO
date and the result is the same...
Why the system doesn't suggest me the planned PO when i fall under 10 days
when i do correlation between the gap of the SO and Toda'ys date minus the
positive day???
|